Proposed FWPS State Match Funded Projects

With the approximately $20 million in State Match funds triggered by the passage of the May 15, 2007, bond measure, the district will be able to provide:

  • Roof repairs or replacements to eleven elementary schools - Adelaide, Brigadoon, Camelot, Green Gables, Lake Dolloff, Lake Grove, Mark Twain, Nautilus, Rainier View, Twin Lakes, and Wildwood.  Sacajawea and Totem Middle Schools, and Decatur High School are also slated for new roofs.
  • New heating systems or new controls for nine elementary schools – Brigadoon, Camelot, Lake Dolloff, Mirror Lake, Nautilus, Star Lake, Twin Lakes, Wildwood, and Woodmont.  Sacajawea and Totem Middle Schools and Thomas Jefferson High School are also on this list.
  • Plumbing upgrades, specifically replacing domestic water systems or connect to gravity sewer systems, at Adelaide, Brigadoon, Lake Grove, and Twin Lakes Elementary Schools and Illahee Middle School.
  • Electrical work, replacing or adding capacity to the electrical distribution systems at Adelaide, Nautilus, and Star Lake Elementary Schools and Totem Middle School.
  • Structural work, specifically additional earthquake reinforcement, at Adelaide, Lake Grove, Mark Twain, Mirror Lake, Olympic View, Twin Lakes, Wildwood, and Woodmont elementary schools, as well as Sacajawea and Totem Middle Schools, Decatur HS, and Memorial Field.   Thomas Jefferson will get new floor system.
  • Replace interior lighting systems at Adelaide, Brigadoon, Lake Dolloff, Mirror Lake, Rainier View, Silver Lake, Star Lake, Twin Lakes, and Woodmont Elementary Schools and Thomas Jefferson High School.  Memorial Field will receive a new field lighting system.
  • Improve parking safety and capacity at Mirror Lake, Olympic View, Twin Lakes, and Woodmont Elementary Schools, Decatur High School and Memorial Field.
  • Replace siding at Brigadoon and Nautilus.
  • Replace existing cinder fields with turf at Brigadoon, Lake Grove, Nautilus, Olympic View, Star Lake, Twin Lakes, Wildwood and Woodmont elementary schools, and all middle schools except Lakota and Sequoyah. Decatur’s track surface will be replaced.  Thomas Jefferson will complete track improvements and replace the turf playing surface with all-weather surface.

State Match Funded Projects

  Awaiting
Planning
In Planning In Progress Complete Comments
ADELAIDE
Roof       X  
Lighting Upgrade       X  
Plumbing X       Summer 2012
Structure       X  
Field       X  
BRIGADOON
Replace Furnaces       X  
Plumbing X       Summer 2012
Repl/Gym Furnace       X  
Lighting Upgrade       X  
Roof       X  
Enclosure       X  
Field       X  
CAMELOT
Repl/ Heat Pumps       X  
Roof Repair       X  
Gym Lighting        X OSPI Energy Grant
ENTERPRISE
Gym Lighting        X OSPI Energy Grant
GREEN GABLES
Roof       X  
Gym Lighting       X OSPI Energy Grant
KILO
Gym Lighting       X OSPI Energy Grant
Field       X  
LAKE DOLLOFF
Replace Boiler       X  
Gym Lighting        X OSPI Energy Grant
Roof       X  
LAKE GROVE
Roof   X     Summer 2012
Field       X  
Plumbing X       Summer 2012
Structure       X  
MARK TWAIN
Roof       X  
Structure   X     Summer 2012
MEREDITH HILL
Gym Lighting        X OSPI Energy Grant
MIRROR LAKE
Structure   X     Summer 2012
Parking X       working w/city on easement
Lighting Upgrade       X  
NAUTILUS
New Roof       X  
Superv. Controls       X  
Replace Boilers       X  
Service Gym Units       X  
Field       X  
Enclosure   X     Summer 2012
Gym Lighting        X OSPI Energy Grant
OLYMPIC VIEW
Field       X  
Structure       X  
Parking   X     Summer 2012
RAINIER VIEW
Lighting Upgrade       X  
Roof       X  
SHERWOOD
Gym Lighting        X OSPI Energy Grant
SILVER LAKE
Lighting Upgrade       X  
STAR LAKE
Lighting Upgrade       X  
Heating System X       Summer 2012
TWIN LAKES
Rep/Gas Furnaces       X  
Rep/Gym Furnace       X  
Lighting Upgrade       X  
Roof     X   Schedule for Spring 2012
Plumbing X       Summer 2012
Structural X       Summer 2012
Field     X   Summer 2012
Parking   X     Summer 2012
WILDWOOD
DDC Controls       X  
Refurb Library AHU       X  
Refurb Gym AHU       X  
Replace 3 fan coils       X  
Fan Coils       X  
Relocate P/LK Uvs       X  
Relocate P/LK Boilers       X  
RPL w/tank w/wh       X  
Roof       X  
Field       X  
WOODMONT
Recondition UV's       X  
Replace Heat Pump       X  
Refrb Library AHU       X  
Refrb cf/rm &adm AHU       X  
Pony Boiler       X  
Controls       X  
Lighting Upgrade       X  
Parking X       Summer 2012
Field       X  
Structure       X  
ILLAHEE
Sewer Line X       2013 City has not completed their sewer 
Field       X  
Gym Lighting        X OSPI Energy Grant
New Boiler       X OSPI Energy Grant
KILO
Field       X  
SACAJAWEA
Replace Boiler       X  
New Controls       X  
Roof     X   Spring 2012
Field   X     Planning with City - 2012
Structural X       Summer 2012
Gym Lighting        X OSPI Energy Grant
SAGHALIE
Field X       Planning with City- 2012
Gym Lighting        X OSPI Energy Grant
TOTEM
Supervisory Controls       X  
Roof       X  
Field       X  
Structural X       Summer 2012
Electrical X       Summer 2012
Gym Lighting        X OSPI Energy Grant
DECATUR
Roof       X  
Field       X  
Parking X       Summer 2012
Structural X       Summer 2012
Gym Lighting        X OSPI Energy Grant
FEDERAL WAY
Gym Lighting        X OSPI Energy Grant
HVAC Commissioning       X OSPI Energy Grant
THOMAS JEFF
New Controls       X  
Repl/Gym AHU       X  
Lighting Upgrade       X  
Field       X  
Structural Floors       X  
TODD BEAMER
Gym Lighting        X OSPI Energy Grant
MEM. FIELD
Field       X  
Track       X  
Structural / Lighting       X  
Parking X        

General Project Definitions

Heat New system and, or controls
Structural
  • Additional earthquake resistance
  • TJHS New floor system
Plumbing
  • Replace domestic water systems or
  • Connect to gravity sewer system
Electrical Replace or add capacity to electrical distribution system
Lighting
  • Replace interior lighting system
  • FWMF replace field lighting system
Parking Improve parking safety and capacity
Fields
  • Replace existing cinder fields with turf or
  • TJHS complete track improvements and replace turf playing surface with all-weather surface
  • DHS Replace entire track surface
  • FWMF Replace track and field surfaces
Enclosure Replace failed siding material
Access Add access accommodations to the entire FWMF facility
TOTAL COST
ALL PROJECTS
$19,950,000

 